North Ogden Transportation Master Plan

Project Summary

2040 Work TripsNorth Ogden City acquired the consulting services of InterPlan to perform an update to their Transportation Master Plan. North Ogden City outlined five main tasks that they wanted the consultant to perform: Establish existing and future traffic volumes, establish required street cross section, special intersection design considerations, 2700 North/Washington Boulevard commercial access plan, and provide final transportation plan update report. A property owners. workshop was held to discuss future access to 2700 North and Washington Boulevard.

Client:

Craig Barker
North Ogden City Community Development Director
801-737-2215

Key Staff:

Vern Keeslar, AICP; Project Manager
Thomas McMurtry

Project Budget: $20,000

Timeframe: October 2008 - February 2009

Link to final document: North Ogden TMP